๐Ÿ—๏ธ 13 Edna Street, Kingswood NSW 2747

G13/002 โ€” Granny Flat
Contract Sum
$200,000
BC4 Lump Sum ยท Signed 26 Apr 2026
Contract Total (incl. Vars)
$209,460
+$9,460 shed demo ยท +$3,850 plumbing
Owner Paid / Outstanding
$93,850
$115,610 outstanding
Contractor Outstanding
$3,500
1 unpaid invoice (DRS Plumbing)

๐Ÿ’ฐ Progress Payment Schedule

StageAmountStatus
1. Deposit$20,000โœ… Paid 26 Apr
2. Base Stage$30,000โœ… Paid 3 Aug
3. Frame Stage$40,000โœ… Paid 7 Aug
4. External Enclosure$40,000โ–ถ Next claim
5. Rough-in & Linings$30,000โณ Not claimed
6. Fit-off Stage 1$20,000โณ Not claimed
7. Practical Completion$20,000โณ Not claimed
$93,850 claimed / $200,000 (47%) ยท $106,150 remaining

๐Ÿ“… Project Timeline

Contract Signed
26 April 2026
Commencement Date
22 June 2026
Construction Period
250 working days
Original Completion
28 June 2027
EOT Status
EOT-G13-002 drafted (+14d)
Extended Completion
12 July 2027 (if EOT signed)
Days Elapsed (calendar)
68 days since commencement
Current Phase
Frame Complete โ€” External Enclosure Next
Milestones
๐Ÿ“ CC Issued โ†’ ๐Ÿ  Commencement 22 Jun โ†’ ๐Ÿ—๏ธ Slab Complete โ†’ ๐Ÿ”จ Frame Complete โ†’ ๐Ÿ—๏ธ Ext. Enclosure โ†’

โฑ๏ธ Extensions of Time

RefReasonDaysOriginalExtendedStatus
EOT-G13-002 Owner-requested shed demolition variation (VAR-G13-001) +14 cal 28 Jun 2027 12 Jul 2027 Drafted โ€” not sent

๐Ÿ“ Variations

RefDescriptionAmountStatus
VAR-G13-001 Shed demolition works $9,460 Not claimed
G13/003 Plumbing โ€” fixtures & fittings $3,850 โœ… Paid
Total variations: $13,310 ยท Paid: $3,850 ยท Unclaimed: $9,460

๐Ÿ’ณ Owner Payment History

DateAmountStageRefNote
26 Apr 2026$20,000DepositG13/002-DEPOSITContract deposit
3 Jul 2026$3,850VariationG13/003Plumbing variation โ€” ING transfer, receipt #648202
3 Aug 2026$30,000Base StageG13/002-BASEBase stage progress payment
7 Aug 2026$40,000Frame StageG13/005Frame stage progress payment โ€” wall & roof framing, tie-downs, roof trusses erected
Total Paid: $93,850 ยท Outstanding (Contract): $115,610 ยท Outstanding (Variations): $5,610

๐Ÿงพ Contractor Invoices hover โ“˜ for payment breakdown

InvoiceFromCategoryAmountR2G PaidTotal PaidBalanceStatus
MID1A to Z ConstructionBase Stage โ€” Slab $20,900 $9,900R2G Payments (MID1):
26 Jun: +$2,344.50 โ€” Hy-Tec concrete Visa
30 Jun: โˆ’$500.69 โ€” Hy-Tec refund
15 Jul: +$4,770.34 โ€” Hy-Tec pending
17 Jul: โˆ’$846.26 โ€” Hy-Tec return
28 Jul: +$4,132.11 โ€” CommBank final
Net R2G: $9,900

Midwest: $11,000 โ€” CommBank
$20,900$0 โœ… Paid
MID2A to Z ConstructionBase Stage โ€” Excavation $3,410 $3,410R2G Payment:
14 Jul: $3,410 โ€” CommBank transfer
BSB 062-428 ACC 1032 6071
$3,410$0 โœ… Paid
G13/003Midwest Building GroupPlumbing Variation $3,850 โ€” $3,850$0 โœ… Paid
INV-017DRS Plumbing AustraliaPlumbing โ€” Internal + Sewer $3,500 โ€” $0$3,500 โŒ Unpaid
BUN-7016Bunnings MinchinburyMaterials โ€” Misc $42.20 $42.20R2G Payment:
15 Jul: $42.20 โ€” Card 406587-499
ED Services Pty Ltd
$42.20$0 โœ… Paid
PWSM131Perfection WindowsMaterials โ€” Windows $4,800 โ€” $4,800$0 โœ… Paid
SBS-420824SBS FenceSite Costs โ€” Toilet Hire $1,372.80 โ€” $1,372.80$0 โœ… Paid
SBS-420730SBS FenceSite Costs โ€” Fence Hire $544.50 โ€” $544.50$0 โœ… Paid
Total Invoiced: $38,419.50
R2G Direct Paid: $13,352
Total Paid: $34,919.50
Outstanding: $3,500

๐Ÿ“Š Cost vs Contract โ€” Base Stage

Contract BudgetInvoicedRemainingFlag
$30,000 $27,852.20 $2,147.80 โš ๏ธ Tight โ€” DRS $3,500 unpaid
MID1 ($20,900) + MID2 ($3,410) + DRS Plumbing ($3,500) + Bunnings ($42.20) against $30,000 base stage budget

๐Ÿ” Critical Stage Inspections

StageDateInspectorCostInvoiceStatus
1. Piering 26 Jun 2026 Aussie Structural Engineers $400 INV023420 โŒ Unpaid
2. Slab Reinforcement 13 Jul 2026 Aussie Structural Engineers $400 INV023420 โŒ Unpaid
3. Frame TBD Aussie Structural Engineers ~$400 โ€” โณ Not yet
4. Wet Area Waterproofing TBD Aussie Structural Engineers ~$400 โ€” โณ Not yet
5. Stormwater Drainage TBD Aussie Structural Engineers ~$400 โ€” โณ Not yet
6. Final / OC TBD Aussie Structural Engineers ~$400 โ€” โณ Not yet
Inspections Complete: 2 of 6
Total Cost To Date: $880
Invoice Status: INV023420 unpaid โ€” $880 overdue since 25 Jul
Est. Remaining: ~$1,600 (4 ร— ~$400)

๐Ÿ“ Project Documents โ€” DocuSeal Status

Doc RefTypeFileDocuSealSigned
G13/002Building ContractBC4 Lump Sum โ€” $200,000N/Aโœ… Signed 26 Apr
CL-G13-002Commencement LetterCommencement-Letter-G13-002-Rev1.pdfโœ… Sub #10โœ… Signed 18 Jul 2026
VAR-G13-001Variation โ€” Shed DemoVAR-G13-001-Shed-Demolition-Rev1.pdfโœ… Sub #12โœ… Signed 18 Jul 2026
DFA-G13-002Demolition Fee AgreementDemolition-Fee-Agreement-Shed-Rev1.pdfโœ… Sub #11โœ… Signed 18 Jul 2026
G13/003Plumbing VariationINV-G13-003-Plumbing-Rev2.pdfโ€”โœ… Sent & Paid
EOT-G13-002Extension of TimeEOT-G13-002-Rev1.pdf (+14 days)โš ๏ธ Not sentโณ Pending
SCF-G13-002Selection ChangeFloor finish: tiles โ†’ hybrid flooringโš ๏ธ Not sentโณ Pending
INV023420Structural InspectionPiering + slab reinforcement inspectionsN/AโŒ $880 unpaid
โœ… 3 signed via DocuSeal by hanminaye@gmail.com on 18 Jul 2026
๐ŸŸ  2 still to send: EOT-G13-002 + SCF-G13-002

๐Ÿ“‹ Tender Scope & Selections

Site Works
โœ… Excavation & piering
โœ… Waffle pod slab
โœ… Under-slab plumbing
โœ… Shed demolition
Structure
โœ… Wall & roof framing
โœ… Roof trusses
โœ… Tie-downs
โณ Cladding & windows
Finishes
โณ Plasterboard & insulation
โณ Tiling โ†’ Hybrid flooring
โณ Painting
โณ Appliances & fit-off
Services
โœ… Internal plumbing (DRS)
โœ… Windows ordered
โณ Electrical rough-in
โณ Waterproofing
Site Facilities
โœ… Toilet hire (26 wks)
โœ… Fence hire (6 mths)
โณ Site signage
Compliance
โœ… Pier inspection
โœ… Slab inspection
โณ Frame inspection
โณ Final OC

๐Ÿ“Œ Project Summary

Current Stage
Frame Complete
โ–ถ Next: External Enclosure ($40,000)
Financial Health
โš ๏ธ Watch
1 unpaid invoice ยท 5 docs pending
Key Actions
6 items
Pay DRS ยท Send 5 docs ยท Claim Ext. Enclosure
๐Ÿ”ด Pay DRS Plumbing INV-017 ($3,500)
๐ŸŸ  Send 5 drafted documents to owner (Commencement, VAR, EOT, SCF, DFA)
๐ŸŸ  Claim External Enclosure Stage progress payment ($40,000)
๐ŸŸ  Pay Aussie Structural Engineers ($880 โ€” INV023420 overdue)
๐Ÿ”ต DocuSeal: SCF-G13-002 still not sent for signing
๐Ÿ”ต EOT-G13-002 needs owner signature before claiming extension
๐ŸŸข Frame Stage complete & paid โ€” External Enclosure next
G13/002 ยท 13 Edna Street Kingswood ยท Han Min Aye ยท Midwest Building Group ยท Last updated 7 Aug 2026